Small kitchen remodel length is typically a major concern for homeowners considering an upgrade. A well-planned kitchen remodel can dramatically transform your space, making it more functional and enjoyable. However, understanding the time involved is crucial to set realistic expectations and plan accordingly.
The total small kitchen remodel length generally ranges between six to eight weeks, depending on the extent of the renovation. Here is a detailed breakdown of each phase with specific timelines to guide your project:
Small Kitchen Remodel Length
1. Planning (1 Week)
The first step in remodeling is thorough planning. During this stage, you’ll finalize your kitchen layout, select cabinet styles, choose colors, and pick finishes like sinks, faucets, and cabinet hardware. Completing this step carefully can save significant time later in the process.
2. Demolition (3-7 Days)
Next comes removing the old kitchen components such as flooring, cabinets, countertops, and appliances. Demolition also involves cleaning up and preparing plumbing and electrical systems for the new layout. Expect this to take from a few days to a week.
3. Marking and Layout (1-2 Days)
After demolition, clear marking and layout for new installations is essential. Your electrician and plumber will mark new locations for electrical outlets, plumbing, and gas lines. This step is particularly important if you’re rearranging appliances or fixtures.
4. Installation of Mechanicals (1 Week)
Installation of mechanical systems—plumbing, electrical, and HVAC—usually takes about a week. Electrical and plumbing installations typically require around two days each, while HVAC adjustments may take a couple more days.
5. Flooring and Drywall (1 Week)
Once the mechanical systems are installed, the next step includes installing insulation and drywall, followed by flooring. Ceramic tile floors usually take 3-4 days, whereas hardwood flooring can take approximately 5-6 days.
6. Cabinets and Countertops (1-2 Weeks)
Installing kitchen cabinets typically takes 1-2 days. Countertops, however, can take longer, particularly if you’re choosing granite or custom-fabricated options. Granite countertops typically require about ten days for fabrication and installation.
7. Finishing Touches (1 Week)
The final step includes painting, installing backsplashes, and setting up appliances and fixtures. Completing the trim work and thorough cleaning will finalize your remodel. Allocate about one week for these finishing touches.
Delays are common due to factors like delayed deliveries, custom orders, or unexpected issues. Adding a buffer of at least one to two weeks can help manage these delays smoothly.
By clearly understanding each remodeling phase and its specific timeline, you can effectively manage your expectations for your small kitchen remodel length.